1st fix carpentry starts at the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

It’s the end of our 26th week and the roofers have now felted all the roofs and almost finished tiling. They would have finished this week had it not been for another 2 days of heavy rain holding them up. With the houses now protected from rain, the carpenters have been able to crack on with internal…

Roof tiles going on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

At the end of our 25th week we’ve taken a big step forwards with felt and tiles on the roofs of plots 3, 4 & 5 and the stairs fitted to plot 4. At last we can now crack on regardless of the weather conditions! Watch this weeks video update to see how the houses…

Dormer roofs craned in on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

At the end of our 24th week we now have dormer roof frames in place on plots 3, 4 & 5 ready for the roofers to start tiling next week. We had hoped to crane the first 4 or 5 dormers in last Friday so the roofers could start this week, but we got let…

Gable walls finished on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

At the end of our 23rd week we’ve topped out the last gable wall, completing the brickwork shells of all 5 plots. Many thanks to the bricklayers, Mick & Family, who have been a pleasure to work with and have done a fantastic job despite having to work around the worse weather conditions they’ve ever…

Carpenters building roofs on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

It’s the end of our 22nd week and as a result of a day lost to Bank Holiday Monday and a couple of days lost to bad weather and problems with our mortar supplier, we’ve not made a great deal of progress this week. However, the bricklayers have now almost finished all the gable walls…

Gable walls topped out on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

At then end of our 21st week on site at Gospel Lane the bricklayers have topped out the gable walls to 3 of the plots, the remaining 2 should be topped out next week. Watch this weeks video update to see how the development is looking now…

Sale agreed on Plot 5 of the new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

Today we’ve agreed a sale, subject to contract, on plot 5 of our development of 5 new homes we’re building off Gospel Lane, Accocks Green, Birmingham. Anyone interested in buying one of the 4 remaining plots should call our sole selling agents, Bairstow eves, on 0121 706 6203 or request a call back without delay…

Gable wall cut-ups going up on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

It’s the end of our 20th week building 5 new homes off Gospel Lane in Acocks Green, Birmingam. This week the bricklayers have been building the Gable walls between the plots, and again have been held up by heavy rain. Watch this weeks video update to see how the development is looking now and the…

Roof Trusses being craned in on the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

It’s the end of our 19th week and this week we’ve craned the roof trusses into position on all 5 plots. Also this week the bricklayers have topped out the end gable to plot 5 and built the cut up between plots 4 & 5. Watch this weeks video update below to see the crane…

Wall plates going on at the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham

by Andy Evans, in Development News

It’s the end of our 18th week and we’re now up to wall plate (horizontal timbers that go on top of the walls for the roof trusses to be fixed to) on plots 2, 3, 4 & 5.  Next week the roof trusses get delivered and craned into position. This week the houses launched for…