1st fix continues at the 5 new homes we’re building for sale on Gospel Lane, Acocks Green, Birmingham
by Andy Evans, in Development News
At the end of our 27th week we’re finally managing to make consistent good progress now we’re no longer at the mercy of the weather! All 5 plots now have finished roofs, window frames installed and glazing installed to plots 4 & 5. The carpenters are cracking on with forming all the stud walls and hot on their heels are the plumbers and electricians with their 1st fixes. Externally the scaffolding has been taken down from plots 3, 4 & 5 and work has started on the drainage connections and levelling the rear gardens.
Watch this weeks video update to see how the houses are looking now…