Foundation Blockwork Starts at Gospel Lane

by Andy Evans, in Development News

Progress has been slow in the last week due to the horrendous weather, with heavy rain showers nearly every day making it difficult or impossible to do much. You’ll see from my video update below how much rain has fallen!!

Foundations being laid at Gospel Lane

by Andy Evans, in Development News

The site has been cleared, the trenches dug, and concrete is being poured and levelled to form the foundations. The build is under way!

Work starts at Gospel Lane, Acocks Green

by Andy Evans, in Development News

Work has now started on our development of 5 homes, just off Gospel Lane, Acocks Green, Birmingham, with the ground works contractor starting clearance and levelling of the site on Monday 2nd April 2012.